Amazon Web Services has broken ground on Project Rise, its $7 billion data center project in Wheatfield, Jasper County, in Northwest Indiana, DatacenterDynamics reported, citing The Times of Northwest Indiana. Ryan Construction is building the campus, which is expected to take several years. AWS plans up to nine buildings on a 304-acre site bought from utility NIPSCO, and the campus will mostly use air cooling, using water about 2% of the year.
AWS will pay $98 million in taxes upfront and contribute $700 million over 30 years, according to the report. AWS economic development principal Scott Eckhardt called it "one of the largest private-sector investments in Jasper County." AWS is investing a combined $33 billion across sites in New Carlisle, Hobart and Wheatfield, part of a November 2025 commitment to add 2.4GW of capacity in Indiana.
DatacenterDynamics also reported, citing the Washington Business Journal, that AWS has spent more than $170 million on land in Loudoun and Fairfax counties in Virginia. Loudoun County's Board of Supervisors is scheduled to vote on a one-year data center pause on November 17.